Question:
Good morning,
This project was supposed to be completed in 2018 and wasn’t is there and update timeframe?
Sidewalk on County Line from Oakwood to rt 9
Thank you,
Response from Mayor Coles:
It was, but we discovered we needed to obtain easements from multiple property owners because the initial easements were taken by the county when County Line was widened several years ago. I hope the project will be completed this year.
Ray
—————–