Gateway Development Commission Secures Full Funding For Hudson Tunnel Project [PHOTOS]

The Gateway Development Commission (GDC) today signed a Full Funding Grant Agreement (FFGA) with the Federal Transit Administration (FTA) for $6.88 billion in federal funding for the Hudson Tunnel Project (HTP) and closed on Railroad Rehabilitation and Improvement Financing (RRIF) loans from the Build America Bureau totaling $4.06 billion to fund the local share of the project.

With these actions, GDC has secured the entire $16 billion commitment needed to complete the HTP. This includes $12 billion in federal funding – the largest federal funding commitment to a rail transportation project in modern history.

“Today marks a significant milestone on the path to ensuring the success of our nation’s most vital infrastructure project,” said New Jersey Governor Phil Murphy. “Thanks to the leadership of our partners, both in Congress and across the Hudson, our federal government will be covering over 70 percent of the total cost of the Gateway Tunnel Project. As the main artery of our nation’s economy continues to be pushed to its limits, we are now one step closer to transforming the 100-year-old infrastructure under the Hudson River. New Jersey thanks the Biden-Harris Administration for delivering this critical investment so that our region’s transportation system will be able to support a new century of American leadership.”

“Gateway is a project that has enormous consequences for the millions of riders who will benefit from it, and it will be a significant driver of economic growth for the entire New Jersey – New York region,” said Port Authority Chairman Kevin O’Toole. “The Port Authority is committed to continue working with our federal and local partners, including through our funding support announced today, in making the nation’s most vital and impactful rail project a reality.”

“Today marks the culmination of securing funding for a project that stands as the most consequential undertaking of our generation and for the next hundred years in this region. The commitment from all levels of government – local, state, and federal – underscores the profound understanding of this project’s significance,” said NJ TRANSIT President & CEO Kevin S. Corbett. “As a primary user of the current tunnels, no one knows better than NJ TRANSIT and our riders about the desperate need for the new tunnels.”

“After years of planning and persistence, the Hudson Tunnel Project’s days of uncertainty are finally behind us. For twenty-three months, we worked tirelessly to complete the funding puzzle for this vital project. Today we have secured the funding needed to see this project through,” said Kris Kolluri, GDC Chief Executive Officer. “I am proud that we navigated the complex FFGA process without missing a single deadline and thankful for our partners in the Biden Administration, Majority Leader Schumer, Governor Hochul and Governor Murphy, our Congressional delegations, and our many other supporters in Washington, New Jersey, and New York whose dedication to this critical project enabled us to reach this milestone. We look forward to continuing to work together through the construction process.”

The HTP will eliminate one of the biggest risks of failure on the Northeast Corridor by building two additional tracks and rehabilitating the existing North River Tunnel, resulting in four modern tracks between New York and New Jersey. The new tunnel will be in service by 2035 and the full rehabilitation of the existing tunnel will be complete by 2038.

The total $16 billion cost of the HTP will be split 70/30 between the federal government and the project’s local partners: New York, New Jersey, and the Port Authority of New York and New Jersey (PANYNJ). This arrangement saves the local partners multiple billions of dollars compared to the original plan to split the project costs 50/50.

The FFGA signed today represents a commitment from FTA to provide $6.88 billion for the HTP through the New Starts Capital Investment Grant (CIG) Program. This is the largest grant in the history of the CIG Program and the largest single funding source for the HTP. The federal government has also committed $3.8 billion to the project through USDOT’s Federal-State Partnership for Intercity Passenger Rail (FSP) Program, $292 million from the Bipartisan Infrastructure Law’s Mega grant program, and $25 million through the Rebuilding American Infrastructure with Sustainability and Equity (RAISE) Program. Amtrak is contributing an additional $1 billion.

The low-interest RRIF loans that GDC closed on today will fund the local share of the project. These three loans, totaling $4.06 billion, represent the largest aggregate loan the USDOT has provided through the RRIF program.

Construction of the HTP started on both sides of the Hudson River in November 2023 and is expected to create 95,000 jobs and generate $19.6 billion in economic activity.

In New Jersey, the Tonnelle Avenue Bridge and Utility Relocation Project is building a new roadway bridge to allow for a connection to the new tunnel portal and an access point for Tunnel Boring Machines. In Manhattan, work is underway on the Hudson Yards Concrete Casing Section 3 (HYCC-3) Project that will preserve a rail right-of-way to link the new Hudson Tunnel to New York Penn Station.

The actions taken today also enable GDC to move forward with heavy construction and tunnel boring activity. Heavy construction will begin in the coming weeks with the Hudson River Ground Stabilization (HRGS) Project, which will stabilize the riverbed on the Manhattan side of the Hudson River to enable the Tunnel Boring Machines to excavate the new tunnel.

By the end of 2024, GDC will have awarded contracts for more than $5 billion in construction activity, including contracts to build sections of the tunnel passing through the Palisades in New Jersey and going through the Manhattan bulkhead under Hudson River Park, and will have ordered the first Tunnel Boring Machine.

This content, and any other content on TLS, may not be republished or reproduced without prior permission from TLS. Copying or reproducing our content is both against the law and against Halacha. To inquire about using our content, including videos or photos, email us at [email protected].

Stay up to date with our news alerts by following us on Twitter, Instagram and Facebook.

**Click here to join over 20,000 receiving our Whatsapp Status updates!**

**Click here to join the official TLS WhatsApp Community!**

Got a news tip? Email us at [email protected], Text 415-857-2667, or WhatsApp 609-661-8668.

1 COMMENT

  1. Let us not forget- this is New Jersey, where cost overruns generally exceed the total approved amount of the contract. And it will employ union workers who are paid $$$$$.

Comments are closed.